Update - 11/2/22
Dates have been updated since the last update:
Dates have been updated since the last update:
Week of Oct 31: Crews are installing the concrete roadway at the intersection on Kautz Road and IL Rt 64.
Week of Oct. 24: Crews are installing the base layer of asphalt. The final asphalt and road surface will be completed by the end of the week.
Work is anticipated to start on Thursday, October 6.
Please see attached maps for areas where work will be taking place on Thursday, October 6 and Friday, October 7.
Anticipated construction work for the week of 9/30 - 10/7
Please Note: All work contingent on weather
During the week of October 3rd, the contractor will be finishing up all the underground water and sanitary pipe work and will begin the road restoration; the first part of this restoration will be the concrete curb and driveway approaches.
On Saturday, September 9, a crew will start grading for the new curb and roadway near the railroad tracks, slowly working north.
Sewer crews will continue to install sewer main to the north during the week of September 12. The Sewer crew is expected to be near the intersection of Rte. 64 and Kautz Road at the end of the week.
Currently the contractor is removing bed rock for the building foundation and subfloors. This work will continue for the next week.
Watch this video of an excavator being removed from the pit.
Anticipated work for the week of August 29 - September 2:
Select driveway approaches will be replaced
Landscaping restoration will begin