Update - 6/16/16
- West Side Streets
- Fellows Street – Utility structure work is scheduled to begin the week of June 20th.
- S. 6th Street - Utility structure work is scheduled to begin the week of June 20th.
Brush Pick-Up – This area is scheduled for brush pick up the week of June 20th and will continue as planned. All brush material should be placed in the parkway outside of the area that the contractor is working. Any questions, please contact the Public Works Department at 630-377-4486.
The work for this project is anticipated to start the week of June 25th, with completion in mid-August.
South Tyler Road from Tyler Road to Cambridge Drive has been stabilized and will be back open to residents who specifically live within these few blocks. Please be advised that this roadway is not intended to be utilized by the general public and is posted with signage at all access location with ROAD CLOSED TO THRU TRAFFIC. Only the residents within the project area should be utilizing this area to access their homes during the evening hours.
Due to weather conditions, South Tyler Road between Ronzheimer and Larson will be temporarily closed.
Residents who live in this area, please park on adjacent side streets during this closure.
Last week, CBI applied the finish coat to the exterior bowl, as well the finish coat to the interior wet and interior dry base cone.
This week, CBI anticipates working on the exterior finish coat or interior dry finish coat, and they will be laying out the logo with tape in the near future.
Construction is scheduled to start the week of 5/31/16. During this week the contractor will be placing the construction signage in the project area, which includes the detour route for the road closure between Cambridge Drive and Tyler Road. They will begin saw cutting the items to be removed, such as sidewalk, curb, driveways and pavement. No removals are scheduled for next week.