Week of November 23, 2015
Please reference the attached project map for specific location updates:
The work completed for the week ending November 21, 2015 included:
Please reference the attached project map for specific location updates:
The work completed for the week ending November 21, 2015 included:
Avalon Court
Completed – Punchlist items outstanding.
8th Street and 8th Court
Completed – Punchlist items outstanding.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Completed
Walnut Ave.
Completed
Crabapple Ln.
Completed – Punchlist items outstanding.
S. 10th Ave
Completed
Stone Dr. and DuKane Dr.
Completed
The water tower construction remains on schedule and the contractor is making excellent progress on this project. Here are several highlights and status of the project thus far.
Work completed to date:
The work completed for the week ending November 14, 2015 included the following:
Scheduled work for the week ending November 21, 2015 will include:
For this weeks update we are breaking the project down into three sections:
Northern Project Limits (S of Country Club Road to Cemetery)
The work completed for the week ending October 24, 2015 included pressure testing of the new watermain from the Q Center south to the cemetery.
The scheduled work for the week ending October 31, 2015 will include chlorination of the line from the Q Center south to the cemetery, inspection of new hydrants as well as flushing and testing of the new watermain from the cemetery south to just south of Allen Lane. Once the pressure test is complete, chlorination and sampling of this line will be performed.
Avalon Court
Completed – Punchlist items outstanding.
8th Street and 8th Court
Completed – Punchlist items outstanding.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Completed.
Walnut Ave.
Completed – Punchlist items outstanding.
Crabapple Ln.
Completed – Punchlist items outstanding.
S. 10th Ave.
Completed – Punchlist items outstanding.
The scheduled work for the week ending October 24, 2015 will include inspection of new hydrants as well as pressure testing of the new north portion of water main from Q Center south to the cemetery. Once the pressure test is complete, chlorination, flushing and sampling of the line will be performed.
The work completed for the week ending October 10, 2015 included the start of replacing all electrofused fittings on the HDPE pipe. The new valve and valve vault to the golf course was installed this week as well.
Avalon Court
Completed – Punchlist items outstanding
8th Street and 8th Court
Completed – Punchlist items outstanding
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Completed
Walnut Ave.
Completed – Punchlist items outstanding
Crabapple Ln.
Completed – Punchlist items outstanding
S. 10th Ave
Completed – Punchlist items outstanding
Stone Dr. and DuKane Dr.