Project News

Week of September 14, 2015

The work completed for the week ending September 12, 2015 included working on flushing and testing of watermain north of the cemetery. Drilling for the connection of the watermain to the maintenance shed at the St. Charles Country Club will also occur. Cleanup efforts on the project site continue.

Week of September 7, 2015

EAST SIDE OF FOX RIVER

Tyler Road
The work completed for the week ending September 5, 2015 included the installation of watermain from Allen Lane south to Wing Lane. Flushing and pressure testing of the watermain began on the north end of the project.

The scheduled work for the week ending September 12, 2015 will include the continued installation of watermain to the south.

Week of August 31, 2015

The work completed for the week ending August 29, 2015 included the cleaning and televising of the watermain on the south end of the project.  Pouring of curb and gutter between Marion Avenue and north of the cemetery as well as permanent patching north of Stonehedge Road occurred this week.  Cleanup efforts on the project site continue.

Week of August 31, 2015

West Side of Fox River

Avalon Court
No work this week. Restoration 1st and 2nd week of September.

8th Street and 8th Court
No work this week. Restoration 1st and 2nd week of September.

Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
No work this week. Restoration 1st and 2nd week of September.     

Week of August 24, 2015

West Side of Fox River

Avalon Court
No work this week

8th Street and 8th Court
No work this week

Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
No work this week    

East Side of Fox River

Walnut Ave.          

Hot Mix Asphalt roadway surface pavement paving.

Crabapple Ln.
No work this week.

S. 10th Ave
Hot Mix Asphalt roadway surface pavement paving.

Stone Dr. and DuKane Dr.

Week of August 24, 2015

The work completed for the week ending August 22, 2015 included the connection between North and Iroquois Avenues.  The contractor has cleaned and televised the watermain for investigation of debris and is in the process of making necessary repairs.  Cleanup efforts on the project site continue.

Week of August 17, 2015

The work completed for the week ending August 15, 2015 included the connection at Marion Avenue.  The contractor televised a section of the watermain for investigation of debris and performed heavy cleaning of the watermain using a swabbing device.  Cleanup efforts on the project site continue.

The scheduled work for the week ending August 22, 2015 will include the re-televising of the watermain prior to flushing and pressure testing to assure that the line has been cleaned thoroughly. 