2019 Street Rehabilitation Project

The City will be undertaking street resurfacing projects at various locations throughout the community aimed at maintaining the current roadway infrastructure.  See project details below and please check back for project updates as we progress through construction.

Project Phase: Construction

Proposed Improvements: This work generally includes repairs to the existing curbs, sidewalks, utilities, and providing a new asphalt roadway surface. 

Contractor:  J.A. Johnson Paving

Construction Engineer:  Chris Gottlieb, P.E., Civil Engineer II
                                          Phone number 630-377-4405
                                          email:  cgottlieb@stcharlesil.gov

Estimated Timeline:  Anticipated May 2019 – September 2019

Project Locations:  See attached location map for the locations of projects.

Road Closures: Short-term road closures may be required at intermittent times.  No long term road closures are anticipated.

Update - 6/13/19

Anticipated construction work for the week of June 17-21

East Side Streets

  • Cedar Avenue – Utility repair work to continue.  Please be advised that temporary road closures will be necessary. 
  • Fieldgate Road – Landscape restoration to be completed.
  • Majestic Oaks Drive –  Asphalt paving to begin.  Landscape restoration to be completed.
  • State Avenue – Landscape restoration to be completed.

West Side Streets

Update - 5/30/19

Anticipated construction work for the week of June 3-7

East Side Streets

  • Cedar Avenue – Utility repair work to begin.  Please be advised that temporary road closures will be necessary.
  • Fieldgate Road – Completion of concrete curb, gutter, and sidewalk repairs.
  • Majestic Oaks Drive – Completion of concrete curb, gutter, and sidewalk repairs.
  • State Avenue – Utility repairs may begin.

West Side Streets

Update - 5/23/19

Anticipated construction work for the week of May 27-231

East Side Streets

  • Cedar Avenue – No work at this time.
  • Fieldgate Road – Utility repair work. Pouring curb, gutter, and sidewalk.
  • Majestic Oaks Drive – Utility repair work. Pouring curb, gutter, and sidewalk.
  • State Avenue - No work at this time. Work anticipated to start after 4th of July.

West Side Streets

Update - 05/14/19

Anticipated construction work for the week of May 20-24

East Side Streets

  • Cedar Avenue – No work at this time. Work anticipated to start after 4th of July.
  • Fieldgate Road – Saw cutting of concrete/pavement is scheduled to begin 5/17. Utility repair work is scheduled to begin 5/20.
  • Majestic Oaks Drive – Utility repair work and saw cutting of concrete/pavement may begin.
  • State Avenue - No work at this time. Work anticipated to start after 4th of July.

West Side Streets

Active Project

Public Contacts