2020 Street Rehabilitation Project

The City will be undertaking street resurfacing projects at various locations throughout the community aimed at maintaining the current roadway infrastructure.  See project details below and please check back for project updates as we progress through construction.

Project Phase: Construction

Proposed Improvements: This work generally includes repairs to the existing curbs, sidewalks, utilities, and providing a new asphalt roadway surface. 

Contractor:  J.A. Johnson Paving

Construction Engineer:  Chris Gottlieb, P.E., Civil Engineer II
                                          Phone number 630-377-4405
                                          email cgottlieb@stcharlesil.gov

Estimated Timeline:  Anticipated May 2020 – September 2020

Project Locations:  See attached location map for the locations of projects.

Road Closures: Short-term road closures may be required at intermittent times.  No long term road closures are anticipated.

Update - 7/9/20

Anticipated construction work for the week of July 13 – July 17

Please Note: All work contingent on weather

East Side Streets

  • N. 2nd Ave. – No work at this time
  • Edward Ave. – Landscape restoration, structure adjustments, asphalt surface
  • Fox Glen Dr. – Landscape restoration, asphalt surface
  • King Richard Circle – Landscape restoration
  • Queen Elizabeth Ct. - Landscape restoration
  • Pinelands Rd. - No work at this time

West Side Streets

Update - 6/19/20

Anticipated construction work for the week of June 22-26

Please Note: All work contingent on weather

East Side Streets

  • N. 2nd Ave. – No work at this time
  • Edward Ave. – Utility repair work, curb and sidewalk saw cutting, removal, and replacement
  • Fox Glen Dr. – Curb and sidewalk saw cutting, removal, and replacement
  • King Richard Circle – Curb and sidewalk saw cutting, removal, and replacement
  • Queen Elizabeth Ct. - Curb and sidewalk saw cutting, removal, and replacement
  • Pinelands Rd. - No work at this time

West Side Streets

Update - 6/11/20

Anticipated construction work for the week of June 15-19

Please Note: All work contingent on weather

East Side Streets

  • N. 2nd Ave. – No work at this time
  • Edward Ave. – Utility repair work including water main and valve replacement
  • Fox Glen Dr. – No work at this time
  • King Richard Circle – No work at this time
  • Queen Elizabeth Ct. - No work at this time
  • Pinelands Rd. - No work at this time

West Side Streets

Update - 5/28/20

Anticipated construction work for the week of June 1-5

Please Note: All work contingent on weather

East Side Streets

  • N. 2nd Ave. – No work at this time
  • Edward Ave. – No work at this time
  • Fox Glen Dr. – Utility repair work and saw cutting of concrete/pavement may begin
  • King Richard Circle – No work at this time
  • Queen Elizabeth Ct. - Utility repair work and saw cutting of concrete/pavement may begin
  • Pinelands Rd. - No work at this time

West Side Streets