Update - 5/19/22
Anticipated construction work for the week of 5/23 - 5/27
The City will be undertaking street resurfacing projects at various locations throughout the community, aimed at maintaining the current roadway infrastructure.
See project details below and please check back for project updates as we progress through construction.
Anticipated construction work for the week of 5/23 - 5/27
Update for the week of 5/16 - 5/20/22
Anticipated work for the week of 5/9 - 5/13/22
Millington - Fire hydrant removal and replacement as well as various utility work. Residents will be notified with a door hanger if they will be impacted by shut downs.
Anticipated work for the week of May 2-6:
Concrete sawcutting to begin April 29th - all streets.
Millington - Utility work to begin