Update - 9/29/22
Anticipated construction work for the week of 9/30 - 10/7
Please Note: All work contingent on weather
The City will be undertaking street resurfacing projects at various locations throughout the community, aimed at maintaining the current roadway infrastructure.
See project details below and please check back for project updates as we progress through construction.
Anticipated construction work for the week of 9/30 - 10/7
Please Note: All work contingent on weather
Anticipated construction work for the week of August 11 - August 21
Please note: All work contingent on weather
Anticipated construction work for the week of August 4 - August 14
Please note: All work contingent on weather
Anticipated construction work for the week of July 28 – August 7
Please Note: All work contingent on weather
Anticipated construction work for the week of July 15 - July 22
Please Note: All work contingent on weather
Milling and resurfacing work are currently on hold due to the Operator Union Local 150’s strike reducing stone material availability. Work will resume as soon as a resolution is reached.
Please Note: All work contingent on weather
Milling and resurfacing work are currently on hold due to the Operator Union Local 150’s strike reducing stone material availability. Work will resume as soon as a resolution is reached.
• East Side Streets
o Illinois Ave. 3rd to 10th – Utility work to begin.
o Illinois Ave. 38th to Kautz – No work anticipated.
o Cumberland Green – No work anticipated.
o Cumberland Pkwy. – No work anticipated.
o N. 2nd Ave. – Concrete curb and gutter and sidewalk removal and replacement