N. 2nd Avenue & Delnor Avenue Improvements

The City has hired WBK Engineering of St. Charles to complete a Concept Engineering Study of this area.  The purpose of this study is to determine the potential infrastructure improvements, which may include; water main replacement, sanitary sewer spot repairs, roadway resurfacing or reconstruction and drainage improvements.  As part of this study WBK Engineering will be evaluating all of the existing field conditions, existing utility conditions and work with the property owners to gain feedback of your experiences. 

  • Project Phase: Final Design
  • Proposed Improvements: Improvements under consideration include utility repairs/replacements and street rehabilitation. 
  • Consulting Engineer:  WBK Engineering of St. Charles, IL. 
  • Estimated Timeline:  Design is anticipated to be complete by the end of 2019
  • Project Locations:  See attached location map for the locations of projects

Update - 01/23/19

At this time, the City has retained WBK Engineering of St. Charles to complete final engineering design, which will incorporate replacement of the water main and the sanitary sewer, as well as storm sewer improvements and roadway reconstruction. 

In 2016, the City requested information from property owners through a questionnaire.  We will be taking the questionnaire responses into consideration to the best of our ability as we move forward.  Specifically, tree removal will be avoided where possible and sidewalk improvements will not be included.