Project Phase: Construction

Proposed Improvements: The City will be installing new water main, storm sewer, and sanitary sewer including new water and sanitary service connections to each house. The City will then perform a full depth reconstruction of both streets with new stone base and asphalt surfacing. Additional work will include replacement of all curbs, sidewalks, and driveway aprons.

Contractor:  Stark and Son Trenching

Resident Engineer:         Justin McKuzes of H.R. Green, Inc. 
                                          Justin cell 815-509-7529
                                          Justin email: jmckuzes@hrgreen.com

Estimated Timeline:  Anticipated May  2019 – September 2019

Project Locations:  Rita Avenue and Nicholas Avenue from Edward Avenue to S. 13th Avenue.

Road Closures: Short-term road closures will be required at intermittent times.  No long term road closures are anticipated.

 

Update - 7/19/19

Next week the contractor will begin landscape restoration and install the new cured-in-place liner on the old sanitary sewer main. Landscape restoration and contract punch list items will continue into early August.

Update - 6/27/19

Upcoming Construction Schedule (Weather Pending)

July 1 – July 5:  Pour new concrete sidewalks.
July 8 – July 12:  Pour new concrete curb and concrete driveway aprons.
July 15 – July 18:  Fine grade roadway, pave asphalt binder and surface.  Pave asphalt driveway aprons.