The City of St. Charles is conducting a sewer and water main replacement project in your neighborhood. Currently the existing infrastructure is in poor condition and frequent breaks cause service outages for local residents. This project will replace and upsize approximately 1,550 liner feet of sanitary sewer and water main along Rte. 31 between Mosedale and Roosevelt Streets. In addition, the project is proposing to replace an additional 2,200 liner feet of sewer main along Roosevelt Street between IL Rte. 31 and Elm Street.  

CONTRACTOR AND INSPECTOR:

The contract for this work has been awarded to Martam Construction, Inc. of Elgin, IL.   Tim Wilson, Public Works Manager – Environmental Service, will be the Project Manager for the City of St. Charles.  The City has hired Engineering Enterprises to be the on-site resident engineer to complete construction inspections for the work and to be your personal construction liaison.  Public Works will be the primary contact regarding any construction activity.  We can be reached at 630-377-4405 or by email at publicworks@stcharlesil.gov.  

START DATES AND COMPLETION DATES:

Expect to see JULIE locates, with construction equipment and staging within the City's easements in middle of April. The majority of the Rte. 31 construction will be completed during the summer. The Roosevelt Street completion will be dependent on the fall weather conditions. The goal is to complete the majority of the Roosevelt Street construction by this November with some landscaping and restoration to be completed in the Spring of 2022.

TRAFFIC IMPACTS:

Construction will start at the intersection of Rte. 31 and Mosedale Street in the early part of May. Rte. 31 will remain open to traffic for the majority of construction, but expect delays due to daily lane closures. At times driveway access will be unavailable during utility repairs, curb and driveway apron replacement.  Notification will be provided in advance of closures.

WATER IMPACTS:

The City will be coordinating scheduled water shutoffs as part of this project with the impacted customers. This will include a door notification of the expected shut down time and date. The City will make every effort to schedule all water main shutdowns; however, the contractor is replacing a deteoriating water main.  As a result, unexpected water main breaks can occur, resulting in an emergency water main shutdown.

MORE INFORMATION:

For more information on this project, please feel free to contact the Public Works Environmental Services Group at 630-377-4405.

Update - 8/16/21

Contractor will be installing sanitary sewer at the intersection of Roosevelt St. and Elm St. Due to the nature of the work, the intersection of Roosevelt and Elm will be closed on Monday and Tuesday. Additionally, new sanitary sewer services will be constructed throughout the week for the following lots:

Update - 8/20/21

Next week the Contractor will be installing sanitary sewer and water main at the locations noted on the map.  Additionally, new sanitary sewer services will be constructed throughout the week for the following lots: 

  • 21 Roosevelt
  • 25 Roosevelt
  • 27 Roosevelt
  • 29 Roosevelt
  • 31 Roosevelt
  • 33 Roosevelt
  • 57 Roosevelt
  • 61 Roosevelt

Residents at these addresses can maintain normal water use. 

Update - 11/12/21

Next week the Contractor will complete the final asphalt.

On Monday, the roads will be swept, and prime coat oil will be applied. The purpose of this prime coat oil is to better bind the first layer of asphalt to the second layer of asphalt. This binding of layers gives the street strength and durability.

Update - 11/8/21

Please note the following schedule changes associated with the Roosevelt Street
roadway improvements:

Week of 11/1/21
•    Thursday, Friday, and Saturday – Structure adjustments
•    Friday – Asphalt driveway apron removal and replacement

Week of 11/8/21
•    Structure adjustments
•    Restoration

Week of 11/15/21
•    Install new asphalt surface course
•    Striping

Update - 11/2/21

Due to the weather forecast, please note the following schedule changes associated with the Roosevelt Street roadway improvements:

Week of 10/25/21
• Site clean up
• Restore driveway access

Week of 11/1/21
• Tuesday – Mill off existing pavement
• Wednesday – Install new asphalt binder course
• Thursday – Start structure adjustments

Week of 11/8/21
• Install new asphalt surface course.
• Start parkway restoration