Rte. 31 & Roosevelt St. Trunk Sewer Main Replacement Project

PROJECT PHASE:

Construction

PROJECT IMPROVEMENTS:

The City of St. Charles is conducting a sewer and water main replacement project in your neighborhood. Currently the existing infrastructure is in poor condition and frequent breaks cause service outages for local residents. This project will replace and upsize approximately 1,550 liner feet of sanitary sewer and water main along Rte. 31 between Mosedale and Roosevelt Streets. In addition, the project is proposing to replace an additional 2,200 liner feet of sewer main along Roosevelt Street between IL Rte. 31 and Elm Street.  

CONTRACTOR AND INSPECTOR:

The contract for this work has been awarded to Martam Construction, Inc. of Elgin, IL.   Tim Wilson, Public Works Manager – Environmental Service, will be the Project Manager for the City of St. Charles.  The City has hired Engineering Enterprises to be the on-site resident engineer to complete construction inspections for the work and to be your personal construction liaison.  Public Works will be the primary contact regarding any construction activity.  We can be reached at 630-377-4405 or by email at publicworks@stcharlesil.gov.  

START DATES AND COMPLETION DATES:

Expect to see JULIE locates, with construction equipment and staging within the City's easements in middle of April. The majority of the Rte. 31 construction will be completed during the summer. The Roosevelt Street completion will be dependent on the fall weather conditions. The goal is to complete the majority of the Roosevelt Street construction by this November with some landscaping and restoration to be completed in the Spring of 2022.

TRAFFIC IMPACTS:

Construction will start at the intersection of Rte. 31 and Mosedale Street in the early part of May. Rte. 31 will remain open to traffic for the majority of construction, but expect delays due to daily lane closures. At times driveway access will be unavailable during utility repairs, curb and driveway apron replacement.  Notification will be provided in advance of closures.

WATER IMPACTS:

The City will be coordinating scheduled water shutoffs as part of this project with the impacted customers. This will include a door notification of the expected shut down time and date. The City will make every effort to schedule all water main shutdowns; however, the contractor is replacing a deteoriating water main.  As a result, unexpected water main breaks can occur, resulting in an emergency water main shutdown.

MORE INFORMATION:

For more information on this project, please feel free to contact the Public Works Environmental Services Group at 630-377-4405.

Update - 9/24/21

Next week the Contractor will complete the installation of water main between Elm and Ash Streets on Monday and will begin excavating pits for drilling of new water services between Ash and Fox Glade Court on Tuesday. Wednesday the intersection of Roosevelt and Elm will be closed for installation of storm sewer. Thursday water service connections between Fox Glade and Ash will be switched from the old main to the new main. Water service reconnections in this section are expected to be completed by the end of the day Friday.

Update - 9/22/21

The intersection of Roosevelt and Elm will be closed during working hours on Thursday while the Contractor installs the last of the new water main. Please plan your travel route accordingly.

Moving forward, weekly construction notices will only be posted on the City’s website and will no longer be handed out door to door. Specific construction notices, such as this one, will continue to be handed out on an as needed basis.

If you have any questions, please call Todd Wells with Engineering Enterprises, Inc. at 773-454-4214 or City Public Works Department at 630-377-4405.

Update - 9/17/21

Next week the Contractor will complete the installation of services from Fox Glade Court to 15 Roosevelt. Prior to your new water service being connected to your old water service an on-site field representative from the City or the contractor will be knocking on your door to let you know your service is about to be transferred over and your water will be temporarily turned off for 5 to 10 minutes. After services are completed through this section, work will continue at the intersection of Elm and Roosevelt on Thursday, continuing toward Ash Street on Friday.

Update - 9/10/21

Next week the Contractor will be installing a small section of water main and water services from Fox Glade Court to 15 Roosevelt. Prior to your new water service being connected to your old water service an on-site field representative from the City or the contractor will be knocking on your door to let you know your service is about to be transferred over and your water will be temporarily turned off for 5 to 10 minutes.

Update - 9/3/21

Next week the Contractor will be installing sanitary sewer services and water services from east of Fox Glade Court to 15 Roosevelt. During sewer service installation, residents at these addresses can maintain normal water use. For the installation of the water services, residents will receive a separate notice informing them when their temporary water loss will occur.

Additionally, water main improvements will occur at the intersection of Fox Glade Court and Roosevelt Street on Tuesday.

No construction work will occur on Monday September 6th.

Update - 9/2/21

The intersection of Roosevelt and Elm will be closed for a few hours on Thursday morning. Please plan your travel route accordingly.

If you have any questions, please call Todd Wells with Engineering Enterprises, Inc. at 773-454-4214 or City Department of Public Works at 630-377-4405.

Pages

Active Project

Public Contacts