South Tyler Road & Production Drive Water Main Replacement

Project Phase: Construction

Project Improvements:  The City of St. Charles is conducting a water main replacement project in your neighborhood. The existing water main is in poor condition and frequent breaks cause service outages for local customers. This project will replace 1,200 linear feet of water main along South Tyler Road between Rte. 64 and Production Drive. In addition, the project will replace an additional 2,305 linear feet along Production Drive between South Tyler Road and Industrial Drive. After the water main is completed a road replacement project will start.

Contractor and Inspector:  The contract for this work has been awarded to Pirtano Construction as the General Contractor for the underground work.   Matt Wilson, Environmental Services Division Manager, will be the Project Manager for the City of St. Charles.  The City has retained Rempe-Sharp to be the on-site resident engineer to complete construction inspections for the work. 

Project Dates:  Expect to see JULIE locates, with construction equipment and staging within City easements in middle of March. The water main installation will be conducted over four months with expected completion in June 2021. A road replacement project will start upon the completion of this water main project.

Traffic Impacts:  The portion of the project along Tyler Road and under Rte. 64 will be directionally drilled. Traffic impacts will be at a minimum with the reduction of a single south bound lane on Tyler Road. The water main construction along Production Drive and Industrial Drive will be a traditional open trench. As a result, lane closures will include some traffic flow impacts and short-term driveway closures. The City will provide traffic updates on this project page.  

Water Impacts:  The City will be coordinating scheduled water shutoffs and notifying impacted cutomers via a door hanger which will provide them with the expected shutoff date and time. The City will make every effort to schedule all water main shutdowns, however, unexpected water main breaks can occur resulting in an emergency water main shutdown.

For more information on this project, please feel free to contact Public Works Environmental Services Group at 630-377-4405.

Update - 3/26/21

Watermain installation crews have moved onto Production Drive, the water main installation will be proceeding west on Production Drive.

Additionally, drilling continues on Tyler Road under IL Rte. 64.  There will be continued traffic control and lane closures in this area.

City Crews will be installing additional valves to support the contractors work next week. There is one water shutdown that is scheduled for 3/29/21.

Update - 3/17/21

Watermain is currently being installed on Industrial Dr. and also under Rt 64 at Tyler Rd.
There is currently traffic control and lane closures in these locations.
The attached map shows water shutdowns for 3/18/21 from 8am – 2pm and 3/22/21 from 8am – 2pm.

 