St. Charles Police Station

Design: FGM Architects, Oak Brook, Ill.                Construction Manager: Riley Construction, Lake Bluff, Ill.

About the Project

The City broke ground on the new 56,000 sq. ft. facility at 1515 W. Main Street on July 23, 2018, on the site of the former Valley Shopping Center. The new police station will replace the current facility, portions of which are nearly 100 years old. The $24.6 million project is expected to be completed by December 2019 and will support the City’s policing operations for the next 50 years. Click the Building Features link at the right for details about the project.

Once It’s Complete…

Click the 3-D Walkthrough Video at the right to take a virtual tour of the new police station and see what it will look like inside.


Construction Updates

5/10/19 Update

1. The main staircase stingers (sides) are in and the pans have been placed.

2. The main vestibule glass wall framing is installed and ready for glass.

3. The first floor lobby drywall has started with the south wall complete.

4. The men’s locker room and workout room flooring is complete.

5. The detention benches have been formed.

5/3/19 Update

1. The first floor drywall is roughly 80% complete. The taping crew will start efforts on the first floor while the flooring contractor takes over the second floor space.

2. The ceiling grid on the second floor is complete in a major portion of the second floor with the addition of light fixtures.

3. The north face of the elevator shaft is complete.

4. The accent tile in the bathrooms is on the mens locker room walls.

4/26/19 Update

1. The excavator started the grading in the back of the building

2. The main staircase drywall is continuing

3. The detentions door frames have been toothed

4. The roof screen is complete

5. The squad garage is in the process of being final graded

4/19/19 Update

1. The first batch of metal panels have been installed.

2. The east stair tower stone work is complete.

3. The paint priming work at the second floor west is ongoing with the corridor and men's locker room being the first complete.

4. The brick work at the east side of the building has started.

5. The showers are installed on the second floor.

4/12/19 Update

1. The roof top units were delivered and placed. The electrician is in the process of bringing permanent power to them.

2. The patio and roof in front of the workout room are both complete, and the concrete under the patio was poured.

3. The main squad garage has been stoned.

4. Walls continue to be closed up on the second floor.

5. The exterior precast painting is complete.

4/5/19 Update

1. The interior lobby stone at the east stair tower is complete.

2. The safety 'gate' has been installed for the elevator install starting in two weeks.

3. The north window frame installation is completel.

4. The east side glazing is complete.

5. The drywall on the second floor continues.

Pages