Woods of Fox Glen - Mainline Cable Replacement

  • Project Phase: Engineering
     
  • Proposed Improvements: 4,600 linear feet of mainline cable replacement using directional drilling and new pipe and cable installation.  Existing cable is nearing estimated 30 year life, and the goal is to replace the cable before any outages occur.   Contractor crews will install the pipe and City crews will follow behind installing the new cable.  Residents can expect to see excavations along Fox Glen Drive and Glenbriar Drive, but the Utility is committed to restoring disturbed areas in a timely and professional manner.  No electric service interruptions are expected to be needed to complete this work.
     
  • Contractor:  Archon Construction, Addison, IL
     
  • Construction Engineer:  City Electric Engineering - Phone number 630-377-4407; email: electric@stcharlesil.gov
     
  • Estimated Timeline:  January 22, 2018 – May 2018
     
  • Project Locations:  See attached location map.

 

Project Status

Active Project