Update - 04/29/21

Martam Construction will continue to pre-dig and locate utilities along IL Rte. 31 and Roosevelt Street during the week of April 26th and May 3rd.

Tree removal and trimming will start the week of May 10 and will be conducted by Homer Tree Services. Maps of the tree trimming and removal can be found under project documents.

Update - 3/26/21

Watermain installation crews have moved onto Production Drive, the water main installation will be proceeding west on Production Drive.

Additionally, drilling continues on Tyler Road under IL Rte. 64.  There will be continued traffic control and lane closures in this area.

City Crews will be installing additional valves to support the contractors work next week. There is one water shutdown that is scheduled for 3/29/21.