Construction
Update - 5/8/23
This week work continues on the site investigation and construction fencing/site containment phase of the project. Installation of additional signage, fencing and other pedestrian/traffic control features will be installed and work will begin on removal and salvage of brick pavers from both the existing east plaza and the roadway bricks for future use on this project and throughout the City. Mobilization of steel and other materials for the new pedestrian ramp is expected in the next 7 to 10 days and demolition of the existing hardscapes (sidewalks, street and planters) is anticipate
Update - Week of May 8
Anticipated construction work for the week of May 8 - May 12
Please note: All work contingent on weather
Update - 05/01/23
The second phase of the 1st Street Plaza Expansion project kicks off today (May 1, 2023) with the project contractor Martam Construction of Elgin, Illinois beginning to mobilized equipment and material to the site. Construction fencing and pedestrian/traffic control will commence this week, followed shortly after by utility investigation and demolition of the existing street and sidewalks.
Update - 3/20/23 - Work for the week of March 20 - March 24
Please Note: All work contingent on weather
Riverside Culvert Replacement Project
Update - 11/2/22
Dates have been updated since the last update:
Update - 10/27/22
- Thursday, October 27 - Broken Curb is being removed.
- Friday, October 28 - Curb replacement and Target entrance removal - North Target entrance will be closed October 28 to November 8
- Friday/Saturday, October 28 and 29 - Grading in the IL Dept.
Update - Oct. 31
Week of Oct 31: Crews are installing the concrete roadway at the intersection on Kautz Road and IL Rt 64.
Update - 10/24/22
Week of Oct. 24: Crews are installing the base layer of asphalt. The final asphalt and road surface will be completed by the end of the week.