You are here

Construction

Week of November 30, 2015

Paving work began today on N. 5th Avenue.  Today the contractor will be working to mill off the top pavement surface from North Avenue to Johnor Lane.   This will be followed by placement of fresh oil on the roadway on Tuesday and paving the remainder of the week.  The roadway will be open to one lane of traffic during this time, with flaggers directing traffic during this work. There will be delays during this work. Once the pavement is completed pavement marking will be placed.

Update for November 25, 2015

Any questions regarding this project, please contact the Public Works Department at 630-377-4405.

All water service connections for this project were completed yesterday!  We appreciate your continued patience and support during this project.  We continue to progress towards completion on this project.  There will NOT be any work taking place on Thanksgiving day and we wish you and yours a wonderful holiday.

The remaining work and anticipated dates (weather dependent) include:

Week of November 16, 2015

West Side of Fox River

Avalon Court
Completed – Punchlist items outstanding.

8th Street and 8th Court
Completed – Punchlist items outstanding.

Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Completed

East Side of Fox River

Walnut Ave.
Completed

Crabapple Ln.
Completed – Punchlist items outstanding.

S. 10th Ave
Completed

Stone Dr. and DuKane Dr.
Completed

Week of November 16, 2015

The work completed for the week ending November 14, 2015 included the following:

  • Restoration of the north section from the cemetery driveway north. 
  • Installation of all water services in the middle section (from Allen Lane to Johnor).
  • The south section (North Ave. to Delnor Glen Drive) will be chlorinated and tested by the end of the week.

Scheduled work for the week ending November 21, 2015 will include:

Week of October 26, 2015

The work completed for the week ending October 24, 2015 included pressure testing of the new watermain from the Q Center south to the cemetery. 

The scheduled work for the week ending October 31, 2015 will include chlorination of the line from the Q Center south to the cemetery, inspection of new hydrants as well as flushing and testing of the new watermain from the cemetery south to just south of Allen Lane.  Once the pressure test is complete, chlorination and sampling of this line will be performed. 

Week of October 26, 2015

West Side of Fox River   

Avalon Court
Completed – Punchlist items outstanding.

8th Street and 8th Court
Completed – Punchlist items outstanding.

Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Completed.     

East Side of Fox River

Walnut Ave. 
Completed – Punchlist items outstanding.

Crabapple Ln.
Completed – Punchlist items outstanding.

S. 10th Ave.
Completed – Punchlist items outstanding.

Week of October 19, 2015

The scheduled work for the week ending October 24, 2015 will include inspection of new hydrants as well as pressure testing of the new north portion of water main from Q Center south to the cemetery.  Once the pressure test is complete, chlorination, flushing and sampling of the line will be performed. 

Pages