Update - 6/10/21
Anticipated construction work for the week of June 14-18
Please note: All work contingent on weather
Anticipated construction work for the week of June 14-18
Please note: All work contingent on weather
Anticipated construction work for the week of June 7-11
Please Note: All work contingent on weather
Work anticipated week of 6/7/21
* Please note all work is weather dependent
Anticipated construction work for the week of June 1-4
Please note: All work contingent on weather
Work anticipated week of 5/31/21
* Please note all work is weather dependent
Tuesday there will be a water shut down to allow the Contractor to lower the water main on Indiana Ave. Lowering the water main is necessary to accommodate the new culvert.
Anticipated construction work for the week of May 24-28
Please Note: All work contingent on weather
Work anticipated for the week of 5/24/21
Indiana Ave will be closed at 7th Ave for pavement, curb, and sidewalk removal to be followed by culvert removal the following week.
Grading will be completed between South Ave and Indiana Ave.
Anticipated construction work for the week of May 17-21
Please Note: All work contingent on weather
Work anticipated for the week of 5/17/21
Indiana Ave will be closed at 7th Ave midweek for pavement, curb, and sidewalk removal to be followed by culvert removal.
Monday - Tree trimming on Roosevelt
Tuesday - Tree removal on Roosevelt and tree trimming on Rt 31. There will be a lane closure on Route 31; expect traffic delays
Wednesday - Root pruning and stump grinding