Update - 6/30/21
Starting the week of July 6th, construction will start on Roosevelt Street. The Contractor will be milling off portions of the pavement in anticipation of the utilities being installed.
Milling operations will occur on Tuesday July 6th and are anticipated to last one day. After milling is completed, the sewer and water main installation will continue up Roosevelt Street starting at Rte. 31.