The City will be base reclaiming Stern Avenue between Kirk Road and Kautz Road as well as Stetson Avenue between Stern Avenue and Swenson Avenue. The current roadway base is structurally insufficient which has resulted in the rapid deterioration of the driving surface. This project will strengthen the base and repave the road, providing a smooth driving surface for years to come.
UPDATES
Planned work 6/20 – 6/26
Please note that all work is weather dependent
Saturday 6/21 Planned watermain shutdown for replacement of utilities on Saturday. Impacted businesses will be notified with door hangers
Thursday 6/26 Planned watermain shutdown for replacement of utilities on Thursday. Impacted businesses will be notified with door hangers
Other Work:
Pre-digging for future water work
Nicor demobilizing and restoring site
Planned work 6/12 – 6/19
Water Main Work:
6/14 Planned watermain shutdown for replacement of utilities on Saturday. Impacted businesses will be notified with door hangers
6/19 Planned watermain shutdown for replacement of utilities on Thursday. Impacted businesses will be notified with door hangers
Nicor onsite lowering gas services
Project will be starting soon! Check back for project updates.
Chris Gottlieb, Public Works Manager - Engineering