Stern and Stetson Avenue Base Reclamation Project

The City will be base reclaiming Stern Avenue between Kirk Road and Kautz Road as well as Stetson Avenue between Stern Avenue and Swenson Avenue. The current roadway base is structurally insufficient which has resulted in the rapid deterioration of the driving surface. This project will strengthen the base and repave the road, providing a smooth driving surface for years to come.

  • Project Phase: Construction

  • Proposed Improvements:
    • Utilities: Replacement of aging storm sewer, water valves, and fire hydrants.
    • Roadway: Replacement of damaged sidewalk and curb and gutters. Base stabilization with cement and asphalt paving.

    • Contractor:  Geneva Construction Company

    • Construction Engineer:  Joshua Schmitt
                                                   Phone number 815.276.2081
                                                   Email jschmitt@hrgreen.com

    • Estimated Timeline:  June 2025 – September 2025

    • Project Locations: Stern Avenue from Kirk Road to Kautz Road
                                        Stetson Avenue from Stern Avenue to Swenson Avenue

    • Road Closures:  Intermittent short-term road closures will be utilized throughout the project. Scheduled weekend closures will be required for base reclamation work.  No long-term road closures are anticipated.

UPDATES

Update - 6/19/25

Planned work 6/20 – 6/26

Please note that all work is weather dependent

Saturday 6/21 Planned watermain shutdown for replacement of utilities on Saturday. Impacted businesses will be notified with door hangers

Thursday 6/26 Planned watermain shutdown for replacement of utilities on Thursday. Impacted businesses will be notified with door hangers

Other Work:

Pre-digging for future water work

Nicor demobilizing and restoring site

 

Update - 6/12/25

Planned work 6/12 – 6/19

Please note that all work is weather dependent

Water Main Work:

6/14 Planned watermain shutdown for replacement of utilities on Saturday. Impacted businesses will be notified with door hangers

6/19 Planned watermain shutdown for replacement of utilities on Thursday. Impacted businesses will be notified with door hangers

Other Work:

Pre-digging for future water work

Nicor onsite lowering gas services

 

Update - 6/3/25

Project will be starting soon!  Check back for project updates.