2026 Roadway Resurfacing Project

2026 Street Rehabilitation Project

The City will be undertaking street resurfacing projects at various locations throughout the community aimed at maintaining the current roadway infrastructure.  See project details below and please check back for project updates as we progress through construction.

  • Proposed Improvements: This work generally includes repairs to the existing curbs, sidewalks, utilities, and providing a new asphalt roadway surface. On certain streets, work will be coordinated with the Lead Service Line Replacement Project in advance of resurfacing. Please see the Lead Service Line Replacement Project construction page for the latest information.
  • Contractor: Geneva Construction Company, LLC
  • Construction Engineer:  Zlatko Nikolov, PE, CFM, Civil Engineer I
                                              Phone Number: 630-377-4405
                                              Email: znikolov@stcharlesil.gov
  • Estimated Timeline:  Anticipated June 2026 – November 2026
  • Project Locations: See attached location map for streets included in this project, including tentative phasing throughout the town.
  • Road Closures: Short-term road closures may be required at intermittent times.  No long-term road closures are anticipated.

UPDATES

Update - 9/25/26

Area 2 (Oak Street incl. side streets & S 3rd St

Concrete removals and replacements are expected to continue next week on Oak St, East of S 9th St. Mid-week, removals are expected to begin on S 3rd St.

Utility repair and replacement work is expected to begin next week in Lead Service Line Area 2 and continue thru the end of the week.

 

Update - 9/17/26

Area 2 (Oak Street incl. side streets & S 3rd St [EXCLUDING LSL Area 2])

Concrete saw-cutting is expected to begin on Monday, September 21st.

Concrete removals and replacements are expected to begin next week on Oak St, East of S 9th St, on Wednesday, September 23rd.

Area 3 (S 2nd Ave, S 3rd Ave, S 4th Ave, S 8th Ave, S 10th Ave, Walnut Ave, Indiana Ave)

Utility structure repair and replacement work is expected to begin on S 2nd Ave on Monday, September 21st.

Utility structure repair and replacement work is expected to begin on S 10th Ave & Indiana Ave on Wednesday, September, 23rd.

 

Update - 9/10/26

Area 2 (Oak Street incl. side streets & S 3rd St [EXCLUDING LSL Area 2])

Fire hydrant, watermain, and valve replacement work is expected to take place next week on Tuesday, 9/15, and Thursday, 9/17, on S 3rd St.

Beginning on Monday, 9/14, thru the end of the day Tuesday, 9/15, S 3rd St will be closed at the intersection with Indiana St. Please seek alternate routes.

Concrete removals and replacements are expected to begin next week on Oak St, East of S 9th St.

 

Update - 9/3/26

Area 2 (Oak Street incl. side streets & S. 3rd St. [EXCLUDING LSL Area 2])

Utility structure repair and replacement work is expected to continue next week on Oak St. between S. 7th St. and S. 3rd St. Daily intersection closures are expected while work is being completed.

 

Update - 8/27/26

Area 2 (Oak Street incl. side streets & S 3rd St [EXCLUDING LSL Area 2])

Utility structure repair and replacement work is expected to continue next week, focusing on S 3rd St, from IL Rt 64 (Main St) headed South. Daily lane closures are expected. Daily intersection closures may be required. 

 

Update - 8/21/26

Area 1 (Stuart’s Crossing, Blackhawk, Charlemagne, & Majestic Oaks Area)

Pavement marking work is expected to begin on Monday, August 24th, and be completed by Tuesday, August 25th.

Area 2 (Oak Street incl. side streets & S 3rd St [INCLUDING Lead Service Line (LSL) Area 1 & 3; EXCLUDING LSL Area 2])

Utility structure repair and replacement work is expected to continue next week, focusing on Oak St from S 9th St to S 3rd St. Beginning on Wednesday, August 26th, utility work is expected to begin on S 3rd St from Prairie St heading North.

Pavement marking work is expected to begin on Tuesday, August 25th, on the streets West of the intersection of Oak St & S 9th St. 

 

Update - 8/13/26

Area 2 (Oak Street incl. side streets & S 3rd St [INCLUDING Lead Service Line (LSL) Area 1 & 3; EXCLUDING LSL Area 2])

All work will progress thru this area generally from the Northwest to the Southeast.

Utility structure repair and replacement work is expected to continue next week, focusing on Oak St from S 9th St to S 3rd St.

Paving the first layer of asphalt is expected to continue on S 19th St, S 18th St, S 17th St, and the Western portion of Oak St to Randall Rd. This work is expected to take place Monday, August 17th, and be completed by Wednesday, August 19th.

Paving the final layer of asphalt is expected to begin on Wednesday, August 19th, starting from the Northwest and progressing to the Southeast throughout the remainder of the week. 

 

Update - 8/4/26

Area 2 (Oak Street incl. side streets & S 3rd St [INCLUDING Lead Service Line (LSL) Area 1 & 3; EXCLUDING LSL Area 2])

All work will progress thru this area generally from the Northwest to the Southeast.

Utility structure repair and replacement work is expected to continue next week, focusing on Oak St from S 9th St to S 3rd St.

Asphalt surface removal is expected to continue on Oak St, between S 14th St to S 9th St. Once Oak St has been completed in this section, the contractor is expected to head back West from S 9th St and begin work on side streets.

Paving the first layer of asphalt is expected to begin on Oak St, between S 14th St to S 9th St, on Monday, August 10th. Once this section of Oak St has been completed, the contractor is expected to head back West from S 9th St and begin work on side streets.

 

Update - 7/30/26

Area 2 (Oak Street incl. side streets & S 3rd St [INCLUDING Lead Service Line (LSL) Area 1; EXCLUDING LSL Areas 2 & 3])

All work will progress thru this area generally from the Northwest to the Southeast.

Utility structure repair and replacement work is expected to continue next week, focusing on Oak St from S 6th St to S 9th St.

Sidewalk and curb replacements are expected to be completed West of S 9th St by Tuesday, August 4th.

Landscape restoration work is expected to begin next week on Tuesday, August 4th.

Asphalt surface removal is expected to begin on Oak St, between S 14th St to S 7th St, on Wednesday, August 5th. 

 

Update - 7/23/26

Area 2 (Oak Street incl. side streets & S 3rd St [EXCLUDING Lead Service Line Replacement Areas 1, 2, & 3])

All work will progress thru this area generally from the Northwest to the Southeast.

Utility structure repair and replacement work is expected to continue next week.

Sidewalk and curb replacements are expected to continue next week and be completed by the end of the week.

Landscape restoration work is expected to begin next week, Wednesday 7/30.

Asphalt driveway repairs are expected to begin towards the end of next week.

Area 1 (Stuart’s Crossing, Blackhawk, Charlemagne, & Majestic Oaks Area)

Work is expected to be completed in this area on Friday, 7/24. No further work is expected next week.

 

Update - 7/20/26

Area 1 (Stuart’s Crossing, Blackhawk, Charlemagne, & Majestic Oaks Area)

Paving the first layer of asphalt is expected to be completed on Tuesday, July 21st, in this area.

Paving the final layer of asphalt is expected to continue on Wednesday, July 22nd, and be completed by the end of the week in this area.

Landscape restoration is expected to be completed by the end of the week.

The contractor will be performing final clean-up in this area by the end of the week.

Area 2 (Oak Street incl. side streets & S 3rd St [EXCLUDING Lead Service Line Replacement Areas 1, 2, & 3])

All work will progress thru this area generally from the Northwest to the Southeast.

Utility structure repair and replacement work is expected to continue this week.

Sidewalk and curb replacements are expected to continue this week.

 

Update - 7/10/26

Area 1 (Stuart’s Crossing, Blackhawk, Charlemagne, & Majestic Oaks Area)

Remaining sidewalk and curb replacements are expected to be completed on Monday, July 13th.

Remaining asphalt driveway repairs are expected to be completed on Monday, July 13th.

Landscape restoration is expected to continue next week throughout the area.

Pavement surface removal (~2 inches) is expected to continue next week, starting Wednesday, July 15th, and be completed by the end of the week.

Paving the first layer of asphalt is expected to continue next week throughout the area.

Paving the final layer of asphalt is expected to begin in the area on Wednesday, July 15th, progressing from the North to the South.

Area 2 (Oak Street incl. side streets & S 3rd St [EXCLUDING Lead Service Line Replacement Areas 1, 2, & 3])

All work will progress thru this area generally from the Northwest to the Southeast.

Utility structure repair and replacement work is expected to continue next week.

Sidewalk and curb replacements are expected to continue next week.

 

Update - 7/9/26

Area 1 (Stuart’s Crossing, Blackhawk, Charlemagne, & Majestic Oaks Area)

Remaining utility structure replacements are expected to be completed on Monday, July 6th.

Remaining sidewalk and curb replacements are expected to be completed by Tuesday, July 7th.

Asphalt driveway repairs are expected to continue and be completed on Monday, July 6th.

Landscape restoration is expected to continue next week throughout the area.

Pavement surface removal (~2 inches) is expected to continue next week progressing from the North to the South.

Paving the first layer of asphalt is expected to begin on Thursday, July 9th, progressing from the North to the South.

Area 2 (Oak Street incl. side streets & S 3rd St [EXCLUDING Lead Service Line Replacement Areas 1, 2, & 3])

Utility structure repair and replacement work is expected to begin on Monday, July 6th and continue thru the end of the week.

Sidewalk and curb replacements are expected to continue next week.

Work will continue to progress in this area generally from the Northwest to the Southeast.

 

Update - 7/2/26

Area 1 (Stuart’s Crossing, Blackhawk, Charlemagne, & Majestic Oaks Area)

Remaining sidewalk and curb replacements are expected to be completed on Monday, July 13th.

Remaining asphalt driveway repairs are expected to be completed on Monday, July 13th.

Landscape restoration is expected to continue next week throughout the area.

Pavement surface removal (~2 inches) is expected to continue next week, starting Wednesday, July 15th, and be completed by the end of the week.

Paving the first layer of asphalt is expected to continue next week throughout the area.

Paving the final layer of asphalt is expected to begin in the area on Wednesday, July 15th, progressing from the North to the South.

Area 2 (Oak Street incl. side streets & S 3rd St [EXCLUDING Lead Service Line Replacement Areas 1, 2, & 3])

All work will progress thru this area generally from the Northwest to the Southeast.

Utility structure repair and replacement work is expected to continue next week.

Sidewalk and curb replacements are expected to continue next week.

 

Update - 6/26/26

Area 1 (Stuart’s Crossing, Blackhawk, Charlemagne, & Majestic Oaks Area)

Utility structure repair and replacements are expected to be completed by Tuesday, June 30th.

Sidewalk and curb replacements are expected to be completed by Tuesday, June 30th.

Asphalt driveway repairs are expected to take place Monday and Tuesday, June 29 – 30th.

Landscape restoration is expected to take place Monday and Tuesday, June 29 – 30th.

Pavement surface removal (~2 inches) is expected to begin on Wednesday, July 1st, and continue thru the end of the week. Work is expected to begin from the North and progress South.

Area 2 (Oak Street incl. side streets & S 3rd St [EXCLUDING Lead Service Line Replacement Areas 1, 2, & 3])

Work in this area is generally expected to progress from the Northwest to the Southeast.

Utility structure repair and replacement work is expected to begin on Wednesday, July 1st.

Sidewalk and curb replacements are expected to begin on Wednesday, July 1st.

 

Update - 6/18/26

Area 1 (Stuart’s Crossing, Blackhawk, Charlemagne, & Majestic Oaks Area)

Next week, the contractor is expected to continue and complete utility structure repair and replacement work by the end of the week.

Sidewalk and curb replacements are expected to continue and be completed by the end of the week.

 

Update 6/15/26

Area 1 (Stuart’s Crossing, Blackhawk, Charlemagne, & Majestic Oaks Area)

Next week, the contractor is expected to continue and complete utility structure repair and replacement work by the end of the week.

Sidewalk and curb removals are expected to begin on Monday and progress from the North to the South thru the area.

Sidewalk and curb replacements are expected to begin on Wednesday and continue through the end of the week.

 

Update - 5/28/26

Please check back for weekly updates once the project is underway.