Area 1 (Stuart’s Crossing, Blackhawk, Charlemagne, & Majestic Oaks Area)
Remaining utility structure replacements are expected to be completed on Monday, July 6th.
Remaining sidewalk and curb replacements are expected to be completed by Tuesday, July 7th.
Asphalt driveway repairs are expected to continue and be completed on Monday, July 6th.
Landscape restoration is expected to continue next week throughout the area.
Pavement surface removal (~2 inches) is expected to continue next week progressing from the North to the South.
Paving the first layer of asphalt is expected to begin on Thursday, July 9th, progressing from the North to the South.
Area 2 (Oak Street incl. side streets & S 3rd St [EXCLUDING Lead Service Line Replacement Areas 1, 2, & 3])
Utility structure repair and replacement work is expected to begin on Monday, July 6th and continue thru the end of the week.
Sidewalk and curb replacements are expected to continue next week.
Work will continue to progress in this area generally from the Northwest to the Southeast.