Area 1 (Stuart’s Crossing, Blackhawk, Charlemagne, & Majestic Oaks Area)
Remaining sidewalk and curb replacements are expected to be completed on Monday, July 13th.
Remaining asphalt driveway repairs are expected to be completed on Monday, July 13th.
Landscape restoration is expected to continue next week throughout the area.
Pavement surface removal (~2 inches) is expected to continue next week, starting Wednesday, July 15th, and be completed by the end of the week.
Paving the first layer of asphalt is expected to continue next week throughout the area.
Paving the final layer of asphalt is expected to begin in the area on Wednesday, July 15th, progressing from the North to the South.
Area 2 (Oak Street incl. side streets & S 3rd St [EXCLUDING Lead Service Line Replacement Areas 1, 2, & 3])
All work will progress thru this area generally from the Northwest to the Southeast.
Utility structure repair and replacement work is expected to continue next week.
Sidewalk and curb replacements are expected to continue next week.