Work for the week of 7/21/25
Please note - all work is weather dependent
Smith Rd Area (Smith Rd, Pheasant Trl, Pheasant Ct)
The Contractor is expected to complete permanent pavement marking this Saturday, July 19.
Brownstone Area (Indiana St, Brownstone Dr, Limestone Dr, Bluestone Dr, Cobblestone Dr)
This area has been substantially completed. The parking stalls in front of the coffee shop and salon need the final layer of surface placed. A timeline for this work is still to be determined.
Southeast St. Charles Industrial Areas (Wallace Ave, Sidwell Ct, Colomba Ct, Legacy Blvd, Equity Dr, Rukel Way, Enterprise Ct)
The first layer of asphalt is expected to be placed on Monday. The final layer of asphalt is expected to be placed on Thursday. Asphalt driveway repairs remain and are expected to be completed before the final layer of asphalt is placed.
Southeast St. Charles Residential Areas (Jobe Ave, Forrest Blvd, Forest Ave, Jeanette Ave, Emery Ct, Moore Ave, Moore Ct, Lucylle Ave, Lucylle Ct, Williams Ave, Midway Ave)
The first layer of asphalt is expected to be placed on Monday on Moore Ave, Moore Ct, Lucylle Ct, and the remainder of Forrest. Placement of the final layer of asphalt is expected to begin on Friday in this area.
Persimmon, Stonehedge, & Fox Chase Area (Marion Ave, Stonewood Dr, Persimmon Dr, Fairway Ct, Persimmon Ct, Fox Ct, Stonehedge Rd, Sutton Pl, Fox Chase Blvd, Tall Grass Ct, Secretariat Ct, Jeffrey Ct, Red Fox Ct, Triple Crown Ct, Surrey Woods Dr, Red Oak Ln, Pin Oak Ln)
Concrete removals and replacements are expected to continue next week.
Williams Ave
7/21 – Final grading is expected to be completed and proof rolling is expected to be performed; base repairs as needed.
7/23 – The first layer of asphalt is expected to be placed.
7/25 – The final layer of asphalt is expected to be placed.
Lucylle Ave
7/21 – Excavation and stone placement is expected to continue.
7/22 – Excavation, stone placement, and final grading are expected to be completed. Proof rolling is expected to be performed; base repairs as needed.
7/23 – The first layer of asphalt is expected to be placed.
7/25 – The final layer of asphalt is expected to be placed.
Jobe Ave
7/25 – The final layer of asphalt is expected to be placed.
North 3rd Ave & Johnor Ave
7/22 – Excavation and stone placement are expected to begin.
7/25 – Final grading is expected to be completed and proof rolling is expected to be performed; base repairs as needed.