Update - 10/20/21
Please note the following schedule changes associated with the installation of the new concrete curb, sidewalk, and aprons on Roosevelt Street:
• Thursday 10/21 – Pouring concrete curb and gutter starting at 7:00 AM
• Friday 10/22 – No Work
• Saturday 10/23 – Framing for concrete
• Monday 10/25 – Pouring remaining curb and pouring sidewalks and aprons starting at 7:00 AM