Please note the following schedule changes associated with the Roosevelt Street roadway improvements:
Week of 11/1/21
• Thursday and Friday – Structure adjustments
• Friday – Asphalt driveway apron removal and replacement
Week of 11/8/21
• Structure adjustments
• Restoration
Week of 11/15/21
• Install new asphalt surface course
• Striping
As with all construction projects of this nature, schedules are weather dependent. We will do our best to notify you of any schedule changes due to inclement weather. If you have any questions, please call Todd Wells with Engineering Enterprises, Inc. at 773-454-4214 or City Department of Public Works at 630-377-4405.