News: Project News

  • Week of August 3, 2015 - 2015 MFT Street Rehabilitation Project

    07/30/2015 - West Side of Fox RiverAvalon CourtPaving complete, Restoration September 1st.8th Street and 8th CourtPaving complete, Restoration September 1st.            Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.Paving complete, Restoration September 1st.East Side of Fox RiverWalnut Ave.No work this week.
  • City of St. Charles Street Resurfacing Program Underway

    07/27/2015 - The City of St. Charles launched its 2015 Street Program Resurfacing project June 29. Work continues, weather permitting. 
  • Week of July 20, 2015 - 2015 MFT Street Rehabilitation Project

    07/27/2015 - West Side of Fox RiverAvalon CourtPavement Grinding, Pavement Patching and Driveway Apron Repairs8th Street and 8th CourtPavement Grinding, Pavement Patching and Driveway Apron Repairs                   Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.Pavement Grinding, Pavement Patching and Driveway Apron Repairs       
  • Week of July 27, 2015 - 2015 MFT Street Rehabilitation Project

    07/27/2015 - West Side of Fox RiverAvalon CourtHot Mix Asphalt, leveling binder and crack prevention material8th Street and 8th CourtHot Mix Asphalt, leveling binder and crack prevention material               Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.Hot Mix Asphalt, surface and crack prevention materialEast Side of Fox RiverWalnut Ave.Concrete street repair and patching
  • Week of July 27, 2015 - North 5th Avenue (Route 25) Water Main Replacement Project

    07/24/2015 - The work completed for the week ending July 25, 2015 included the Allen Lane connection as well as the fire hydrant installation at this location. The connection at North Avenue was also completed with the associated fire hydrant.  Flushing and pressure testing of the new watermain has not yet been scheduled due to delivery of needed parts. Contractor has begun restoration of curb and gutter.
  • Friday, July 24, 2015 - Peck Road Resurfacing Project

    07/23/2015 - Work scheduled for Friday, July 24 and Saturday, July 25 is as follows:Pavement prime coat (Fresh Oil) being placed at sunrise on Saturday.Concrete curb and sidewalk saw cutting, forming and pouring new concrete curb and sidewalks.Utility structure adjustments.Pavement grinding and pavement patching, mid-week through the end of the week. 
  • Week of July 27, 2015 - Peck Road Resurfacing Project

    07/23/2015 - Work for the week of July 27 is as follows:Hot Mix Asphalt - leveling binder placementStructure adjustements in roadway pavementTraffic signal loops at Route 64Roadway ditch grading north of Voltaire LaneCrack prevention material placement (Petromat)
  • Week of July 20, 2015 - North 5th Avenue (Route 25) Water Main Replacement Project

    07/22/2015 - The work completed for the week ending July 18, 2015 included fire hydrant installation at Allen Lane on 5th Avenue. Connections were also completed this week at connections at Delnor, private drive and Marion.  Flushing and pressure testing of the new watermain has not yet been scheduled due to delivery of needed parts.
  • Week of July 20, 2015 - Peck Road Resurfacing Project

    07/16/2015 - Work for the week of July 20, 2015 will consist of:Concrete curb and sidewalk saw cutting, forming and pouring new concrete curb and sidewalksUtility structure adjustmentsPavement grinding and pavement patching, mid-week through the end of the week
  • Week of July 13, 2015 - 2015 MFT Street Rehabilitation Project

    07/13/2015 - WEST SIDE OF FOX RIVERAvalon CourtCurb and sidewalk removal and replacement8th Street and 8th CourtCurb and sidewalk removal and replacmentUtility work in street (Replacement of storm sewer structures)Greenwood Lane, Mockingbird Court and Oxmoor CourtCurb and sidewalk removal and replacementEAST SIDE OF FOX RIVERWalnut AvenueUtility work in street (Replacement of water main structures)Crabapple LaneCurb and sidewalk removal and replacement
  • Week of July 13, 2015 - North 5th Avenue (Route 25) Water Main Replacement Project

    07/13/2015 - The work completed for the week ending July 11, 2015 included the continued installation of fire hydrants and valve vaults along 5th Avenue. The Stonehedge Road and North Avenue side street connections were also completed this week.  Flushing and pressure testing of the new watermain has been postponed until correct parts are obtained.
  • Week of July 13, 2015 - Peck Road Resurfacing Project

    07/10/2015 - Work for the week of July 13 is scheduled as follows:Curb and sidwalk, saw cutting, removal, forming and pouring new curb and walk.Utility structure adjustments.Pavement grinding scheduled for Friday or following week.
  • Week of July 6, 2015 - 2015 MFT Street Rehabilitation Project

    07/09/2015 - West Side StreetsSaw cutting started on west side streets the week of June 29. Storm sewer work started on Avalon Court the week of June 29 and has been completed.  Additional saw cutting, curb, sidewalk and utility repairs are scheduled to take place on west side streets the week of July 6. The affected streets are Greenwood Lane, Oxmoor Court, Mockingbird Court, Crabapple Lane, Avalon Court, South 8th Street and 8th Court.East Side StreetsSaw cutting may be taking place on some east side streets the week of July 6.N. Tyler RoadNo work.
  • DUPAGE COUNTY FEMA Mapping Revisions

    07/09/2015 - The City of St. Charles was notified by the Illinois State Water Survey (ISWS) on behalf of the Federal Emergency Management Agency (FEMA) that they are hosting an Open House meeting to present the newly produced digital Flood Insurance Rate Map (FIRM) and Flood Insurance Study (FIS) for DuPage County, Illinois and Incorporated areas.
  • Week of July 6, 2015 - North 5th Avenue (Route 25) Water Main Replacement Project

    07/02/2015 - The work completed for the week ending July 4, 2015 included the continued installation of fire hydrants and valve vaults along 5th Avenue. The Iroquois side street connection was also completed this week.  Flushing and pressure testing of the new watermain has been postponed until correct parts are obtained.