News: Project News

  • Week of August 31, 2015 - North 5th Avenue (Route 25) Water Main Replacement Project

    08/28/2015 - The work completed for the week ending August 29, 2015 included the cleaning and televising of the watermain on the south end of the project.  Pouring of curb and gutter between Marion Avenue and north of the cemetery as well as permanent patching north of Stonehedge Road occurred this week.  Cleanup efforts on the project site continue.
  • Week of August 31, 2015 - 2015 MFT Street Rehabilitation Project

    08/28/2015 - West Side of Fox RiverAvalon CourtNo work this week. Restoration 1st and 2nd week of September.8th Street and 8th CourtNo work this week. Restoration 1st and 2nd week of September.Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.No work this week. Restoration 1st and 2nd week of September.     
  • Week of August 24, 2015 - 2015 MFT Street Rehabilitation Project

    08/21/2015 - West Side of Fox RiverAvalon CourtNo work this week8th Street and 8th CourtNo work this weekGreenwood Ln., Mockingbird Ct. and Oxmoor Ct.No work this week    East Side of Fox RiverWalnut Ave.          Hot Mix Asphalt roadway surface pavement paving.Crabapple Ln.No work this week.S. 10th AveHot Mix Asphalt roadway surface pavement paving.
  • Week of August 24, 2015 - Peck Road Resurfacing Project

    08/21/2015 - All work is completed at this time except for punch list items.
  • Week of August 24, 2015 - North 5th Avenue (Route 25) Water Main Replacement Project

    08/20/2015 - The work completed for the week ending August 22, 2015 included the connection between North and Iroquois Avenues.  The contractor has cleaned and televised the watermain for investigation of debris and is in the process of making necessary repairs.  Cleanup efforts on the project site continue.
  • Week of August 17, 2015 - Peck Road Resurfacing Project

    08/13/2015 - Work for the week of August 17 is as follows:Placement of pavement stripingPacement of roadway shoulder at north end of projectPlacement of driveway aprongsPlacement of topsoil with seed and seed blanket behind new curb and sidewalks
  • Week of August 17, 2015 - North 5th Avenue (Route 25) Water Main Replacement Project

    08/13/2015 - The work completed for the week ending August 15, 2015 included the connection at Marion Avenue.  The contractor televised a section of the watermain for investigation of debris and performed heavy cleaning of the watermain using a swabbing device.  Cleanup efforts on the project site continue.The scheduled work for the week ending August 22, 2015 will include the re-televising of the watermain prior to flushing and pressure testing to assure that the line has been cleaned thoroughly. 
  • Week of August 17, 2015 - 2015 MFT Street Rehabilitation Project

    08/13/2015 - West Side of Fox RiverAvalon CourtNo work this week.8th Street and 8th CourtNo work this week.Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.No work this week.  East Side of Fox RiverWalnut Ave.Hot Mix Asphalt pavement grinding.Hot Mix Asphalt pavement paving.Crabapple Ln.No work this week.S. 10th AveHot Mix Asphalt pavement grinding.Hot Mix Asphalt pavement paving.
  • Work Gets Underway on First Street

    08/10/2015 - Preliminary Site Work to Begin ShortlyConstruction fencing will be going up on First Street in the next two weeks as preliminary site work for Phase 3 gets underway. Phase 3 includes construction of three mixed-use buildings and a two level public parking deck in an area bounded by 1st Street, Illinois Street and the Fox River.
  • Week of August 10, 2015 - South Tyler Road Reconstruction

    08/10/2015 - Check back in Spring 2016 for project updates.
  • Week of August 10, 2015 - 2015 MFT Street Rehabilitation Project

    08/10/2015 - West Side of Fox RiverAvalon CourtNo work this week.8th Street and 8th CourtNo work this week.Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.No work this week.East Side of Fox RiverWalnut Ave. Concrete pavement base. HMA pavement grinding. Brick sidewalk repair.Crabapple Ln.No work this week.S. 10th Ave Concrete sidewalk repair.
  • Week of August 10, 2015 - Peck Road Resurfacing Project

    08/07/2015 - Work for the week of August 10 is as follows:Crack prevention material placement (Petromat)Hot Mix Asphalt - roadway surface placementRestoration behind new curb and sidewalks
  • Week of August 3, 2015 - North 5th Avenue (Route 25) Water Main Replacement Project

    08/03/2015 - The work completed for the week ending August 1, 2015 included starting on the Marion Avenue connection as well as the fire hydrant installation at this location.  Flushing and pressure testing of the new watermain has begun.  The contractor has begun restoration of curb and gutter.
  • Week of August 3, 2015 - Peck Road Resurfacing Project

    07/31/2015 - Work for the week of August 3 is scheduled as follows:Restoration behind new curb and sidewalksCrack prevention material placement (Petromat)Hot Mix Asphalt - roadway surface placement
  • Week of August 3, 2015 - 2015 MFT Street Rehabilitation Project

    07/30/2015 - West Side of Fox RiverAvalon CourtPaving complete, Restoration September 1st.8th Street and 8th CourtPaving complete, Restoration September 1st.            Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.Paving complete, Restoration September 1st.East Side of Fox RiverWalnut Ave.No work this week.