Update - 6/14/18
Next week the contractor will continue utility repairs and may begin removal and replacement of curbs and sidewalks.
Update - 6/14/18
Construction is set to begin next week with staging of traffic control and sawcutting of concrete curbs, sidewalks and impacted driveways.
Update - 6/11/18
Construction kicks off this week with utility locates, sawcutting and utility repairs.
Kane County DOT Improvements to Randall Road Begin May 21
The Kane County Department of Transportation has several resurfacing projects planned throughout the county in 2018. In St. Charles, improvements to Randall Road from IL Route 38 to Oak Street are included. Work is anticipated to start the week of May 21 and continue throughout the summer. Temporary lane closures are required for this work, with flaggers directing traffic.
Ohio Avenue Project Limits
2018 Road Construction Map
Update - 4/27/18
Weather delayed some work inside the station. The 35kV feed to the station was energized the week of April 23. Structural aluminum has been delivered and major electrical components are either on site, received and in City inventory, or on order with near term delivery.
Update - 4/27/18
Weather delayed the contractor being able to start; the contractor is now scheduled to start the week of May 7.
Lakeshore Refuse & Recycling Information
As of September 10, Lakeshore Recycling Systems has sent out its initial bills for waste services to the residents of St. Charles. These invoices will be for the months of July, August and September. The next round of bills will be sent out at some point in mid-November. That will cover the months of October, November and December. Beyond that, Lakeshore will begin billing at the start of each quarter.