You are here

Week of July 15, 2013

Underground utility work continues with the installation of storm sewer pipe, and excavation for and installation of approximately 140 feet of 4” SDR 35 sleeve for the new gas service to the new building.

Walls for the first two floors of the south end of the building and storage tanks have been erected as well as the truck bay area.  Additional work completed aligning the exterior Aeration Basin Blowers on the equipment pad east of the existing building.

created Jul 11, 2013 updated Mar 23, 2018