Week of July 22, 2013

Utility work on South 7th Street and South 5th Street has been completed and concrete work including, curb, sidewalk and driveways is scheduled for this week.

Asphalt grinding and paving contractor is scheduled to remove and replace the roadway surface starting the week of July 29th.

The grinding, resurfacing and striping of public parking lots at the southeast corner of Second Street (Route 31) and West Main Street, and at the northwest corner of Third Avenue and East Main Street is now complete.

All residents and businesses that are within the affected construction limits have received a master notification letter describing the projects limits, and anticipated work activities. Additional construction notices will be delivered prior to each phase of the project.

created Jul 22, 2013 updated Jul 30, 2013