Week of September 9, 2013

The Contractor will be focusing on performing joint repairs on the existing concrete roadway between Kirk Road and 38th Avenue.  This work is expected to be completed by September 16, 2013.  Once these repairs have been made, the Contractor will begin placement of the new asphalt roadway along this same section.  These paving activities are expected to be completed by September 20, 2013.

To read the complete update, download the attached document.