Week of October 12, 2015

The work completed for the week ending October 10, 2015 included the start of replacing all electrofused fittings on the HDPE pipe.  The new valve and valve vault to the golf course was installed this week as well.

The scheduled work for the week ending October 17, 2015 will include inspection of new hydrants as well as flushing and testing of the new watermain from the Q Center south to the cemetery.  Once the pressure test is complete, chlorination of the line will be performed.  The contractor will provide notifications to those residents affected by construction who may have restricted access to their driveways during this work 48 hours in advance.

All work schedules are weather dependent.  Daily lane closures should be expected on IL Route 25 for the above work this week.

 