You are here

Update - 8/12/16

The paving work is starting to wrap up for this year’s program.  The contractor will begin placing the topsoil in areas where the parkways have been disturbed over the next week.  Sod restoration to take place in early September.  Once all work below is completed the contractor will address any outstanding punch list items over the next few weeks. 

  • West Side Streets
    • Ash Street, Pine Street, S. 15th Street – Final paving is scheduled for next week.
    • Fellows Street & S. 6th Street – Paving work has been completed.
  • East Side Streets
    • Highgate Course Area – The paving work planned for today has been delayed due to the weather conditions.  The paving work will now take place early next week when weather conditions allow. 
    • Industrial Drive – The paving work is scheduled to take place next week.
    • Kautz Road – The final paving work is anticipated to take place on Saturday, September 19th. 
created Aug 12, 2016 updated Mar 23, 2018

For more information