Anticipated construction work for the week of July 3-7:
East Side Streets
- Banbury Avenue and Court – No work at this time.
- Bent Avenue - No work at this time.
- Dunham Place – Utility repairs may continue.
- N. 3rd Avenue – No work at this time.
- Pleasant Avenue – Concrete curb, sidewalk and driveway removal and replacements to continue.
- S. 14th Avenue – No work at this time.
West Side Streets
- N. 5th Street - No work at this time.
- S. 13th Street & Fellows Street – Water main installation to continue.
- S. 14th Street - No work at this time.