- The permanent fencing has started on the south side of the project. The temporary will remain for a short time until we have a substantial amount in place to keep a level of security.
- The rip rap (larger stone typically placed at various utility structures – in our case the pond inlets and outlets) has been placed at the pond and the native plugs have been holding nicely.
- The first and second phases of epoxy floors are complete. This includes the evidence garage and lab area.
- The above ceiling inspection in the main lobby and training room was successfully passed on Thursday which meant that ceiling tile could continue to be dropped in place.
- Interior finishes continue, including room signage and flooring on the first floor (photo of the elevator included)