Update 7/27/23 – Anticipated construction work for the week of July 30 – Aug 5
Please Note: All work contingent on weather, street access will be maintained during asphalt milling.
East Side Streets
- Fox Chase Blvd. – Asphalt patching, level binder, detector loop replacement
- Hampton Course – Landscape restoration
- Lexington Ave. – Concrete restoration, landscape restoration
- Lancaster Ave. – Concrete restoration, landscape restoration
- Liberty Ave. – Concrete restoration, landscape restoration
- Liberty Ct. – Concrete restoration, landscape restoration
- Cranbrook Ave. – Concrete restoration, landscape restoration
West Side Streets
- River View Dr. – Asphalt binder and surface
- River Ridge Dr. – Asphalt binder and surface, detector loop replacement
- Prairie Crossing Dr. – General cleanup
- Renard Ln. – General cleanup
- Voltaire Ln. – General cleanup
- Provence Dr./Ct. – General cleanup
- Antoine Pl./Ct. – General cleanup