Anticipated construction work for the weeks of October 16 - October 30

Please note:  All work contingent on weather 

Week of October 16

Monday, 10/16/23 - Curb and sidewalk poured adjacent to the pavement replacement

Tuesday, 10/17/23 - Concrete pours in the prepared roadways sections.

Wednesday, 10/28/23 - additional pour if needed

Three days required for concrete to set-up

Week of October 23 

Monday, 10/23 - remove curb, sidewalk and pavement

Tuesday, 10/24 and Wednesday, 10/25 - Curb and sidewalk poured adjacent to the pavement replacement

Thursday, 10/26 - Concrete pours in the prepared roadways sections.

Three days required for concrete to set-up

Week of October 30 

Asphalt repairs and landscape restoration 

created Oct 18, 2023 updated Oct 18, 2023