Riverside Lift Station Replacement Project

The proposed project will include removal of the existing Riverside Lift Station, which is located at the intersection of Riverside Avenue (Illinois Route 25) and Devereaux Way.  A new lift station will be constructed adjacent to the current structure.  The lift station will include a new dual wet well concrete structure, with a capacity of 35 million gallons per day (MGD).  The existing sanitary sewer will be extended to the new lift station location and will be screened prior to entering the wet wells.  Vehicle access to the station, as well as public areas around the lift station, will be improved.  The lift station will be integrated into the existing Supervisory Control and Data Acquisition (SCADA) system.  A new emergency, back-up generator, as well as a new odor control system will also be installed. 

Update - 8/16/23

*REMINDER*

South Riverside Ave./IL Rt. 25 Closed until early October for Work on Riverside Lift Station

South Riverside Ave./IL Rt. 25 in St. Charles will be closed beginning August 16, 2023 until early October 2023. Traffic will be routed to IL Rt. 31 through posted detours at Main St./IL Rt. 64 to the north and State St./IL Rt. 38 to the south. The closure is required for work on the City of St. Charles Lift Station construction project at Riverside Ave./IL Rt. 25 and Deveraux Way.

Update - 7/28/23

Starting August 16th through the beginning of October, South Riverside Ave (IL Rte. 25) will be closed to thru traffic. Regional traffic will be asked to follow the Illinois Department of Transportation approved detour routes of IL Rte. 64 and IL Rte. 38. This regional route is shown in red on the attached map.

Local traffic to homes and business will be allowed. South Riverside Ave will be open to local access up to Langum Park as shown on the map (black dashed line). Traffic will not be able to pass or access the work zone area identified on the attached map.

Update - 7/29/22

The Riverside Lift Station Project is underway and the Jones Law Office has been moved.  New sidewalk to the law office was installed, and over the next several weeks, deteriorating wood on the Jones Law Office will be repaired.  

The contractor will be starting the excavation for the new lift station. 

Active Project

Public Contacts