You are here

Construction, Road

Update - 10/16/23

Anticipated construction work for the weeks of October 16 - October 30

Please note:  All work contingent on weather 

Week of October 16

Monday, 10/16/23 - Curb and sidewalk poured adjacent to the pavement replacement

Tuesday, 10/17/23 - Concrete pours in the prepared roadways sections.

Wednesday, 10/28/23 - additional pour if needed

Three days required for concrete to set-up

Week of October 23 

Monday, 10/23 - remove curb, sidewalk and pavement

Update - 9/14/23

The work on all streets for this project has been substantially completed. The Contractor will be continuing to perform final cleanup, landscaping, and other minor “punchlist” tasks in the upcoming weeks.

Update - 8/31/23

Anticipated construction work for the week of Sept 3 – Sept 9

Please Note:   All work contingent on weather

 ***There will be no work on Monday 9/4 for the Labor Day holiday

East Side Streets

Update - 8/11/23

Anticipated construction work for the week of Aug 13 – Aug 19

Please Note: All work contingent on weather

Base reclamation work to begin on Monday 8/14/23. See below for detailed construction schedule. Please do not park on the street once the pavement has been removed.

Update - 8/3/23

Anticipated construction work for the week of Aug 6 – Aug 12

Please Note: All work contingent on weather

Pavement milling on Lexington/Liberty/Lancaster/Cranbrook and Hampton Course is scheduled to start the week of 8/14. Please check the website regularly for updates.

Update - 7/28/23

Update 7/27/23 – Anticipated construction work for the week of July 30 – Aug 5

Please Note: All work contingent on weather, street access will be maintained during asphalt milling.

East Side Streets

Pages