Update - 4/27/18

Weather delayed some work inside the station.  The 35kV feed to the station was energized the week of April 23.  Structural aluminum has been delivered and major electrical components are either on site, received and in City inventory, or on order with near term delivery.

created Apr 27, 2018 updated Apr 27, 2018