You are here

Project News

Update - 5/28/20

Anticipated construction work for the week of June 1-5

Please Note: All work contingent on weather

East Side Streets

N. 2nd Ave. – No work at this time

Edward Ave. – No work at this time

Fox Glen Dr. – Utility repair work and saw cutting of concrete/pavement may begin.

King Richard Circle – No work at this time

Queen Elizabeth Ct. - Utility repair work and saw cutting of concrete/pavement may begin.

Pinelands Rd. - No work at this time

West Side Streets

Fairview Dr. - No work at this time.

Heritage St./Ct. - No work at this time

Horne St. – No work at this time

Update - 5/26/2020

The construction contract has been approved by City Council, and is anticipated to begin the week of June 1st.  Letters have been sent to impacted residents.  (See project webpage attachments for PDF version of the letter.)

8/30/19 Update

The Police Station is nearing completion. Here are five items that were completed this week:

  1. The Insulguard door and window are installed and finished. These are the specialty storm doors for the community restitution area storm shelter.

8/23/19 Update

  1. The furniture install is complete, and we are working on final cleaning touch ups.
  2. The remaining lockers and vault equipment have been installed.
  3. The landscaping work is complete with some minor touch up work needed at added areas on the nearby streets.

Pages