Update - 8/2/18

The City’s contractor, Archon, has completed 90% of the pipe work, and landscape restoration of disturbed areas is underway.  The pipe work should be 100% completed within the next week.  Soon thereafter, City crews will start to install brand new cables in the pipe.  That work is expected to take 3 to 4 weeks, with the result being a more reliable system for the area.