Update - 8/2/18

The City’s contractor, Archon, has started foundation work for the piers that will support the electrical bus.  That work is anticipated to take 2 weeks.  City crews will start work after that to install the aluminum structure and electrical bus.  Commissioning and in-service for the substation is anticipated to be prior to the end of the year.

created Aug 02, 2018 updated Aug 02, 2018