Update 7/31/20

Anticipated construction work for the week of August 3 – August 7

Please Note: All work contingent on weather

• East Side Streets
o N. 2nd Ave. – No work at this time

o Edward Ave. – No work at this time

o Fox Glen Dr. – No work at this time

o King Richard Circle – No work at this time

o Queen Elizabeth Ct. - No work at this time

o Pinelands Rd. - No work at this time

• West Side Streets
o Fairview Dr. – Asphalt surface removal and preparation for new asphalt pavement.

o Heritage St./Ct. - No work at this time

o Horne St. – Concrete curb and gutter and sidewalk to be completed, Asphalt surface removal and preparation for new asphalt pavement.

o Killdeer Ln. – No work at this time

o S. 12th St. – Potential asphalt surface removal and replacement

o S. 19th Street – Asphalt surface removal and preparation for new asphalt pavement.

o Tradition Blvd. – No work at this time

updated Jul 31, 2020