Update - 8/16/21

Contractor will be installing sanitary sewer at the intersection of Roosevelt St. and Elm St. Due to the nature of the work, the intersection of Roosevelt and Elm will be closed on Monday and Tuesday. Additionally, new sanitary sewer services will be constructed throughout the week for the following lots:

20 Roosevelt36 Roosevelt
24 Roosevelt38 Roosevelt
28 Roosevelt45 Roosevelt
30 Roosevelt57 Roosevelt
32 Roosevelt61 Roosevelt
34 Roosevelt 

 

Residents at these addresses can maintain normal water use. The contractor will also resume water main installation on Thursday. A map of the approximate work zones is attached. Construction is a moving operation; therefore, the work zones will change daily.

On-street parking will be prohibited in the work zone. Residents with driveways within the active work zones are asked to relocate their car(s) to an available location on Roosevelt Street or to a side street by 7 a.m.

As a reminder, notifications are posted on the City’s website at https://www.stcharlesil.gov/projects.

If you have any questions, please call Todd Wells with Engineering Enterprises, Inc. at 773-454-4214 or City Department of Public Works at 630-377-4405. 