Update - 8/16/21

Next week the Contractor will be installing sanitary sewer at the intersection of
Roosevelt St. and Elm St. Due to the nature of the work, the intersection of
Roosevelt and Elm will be closed on Monday and Tuesday. Additionally, new
sanitary sewer services will be constructed throughout the week for the following lots:

• 20 Roosevelt
• 24 Roosevelt
• 28 Roosevelt
• 30 Roosevelt
• 32 Roosevelt
• 34 Roosevelt
• 36 Roosevelt
• 38 Roosevelt
• 45 Roosevelt
• 57 Roosevelt
• 61 Roosevelt

Residents at these addresses can maintain normal water use. The contractor will also
resume water main installation on Thursday. A map of the approximate work zones is
attached. Construction is a moving operation; therefore, the work zones will change
daily.

On-street parking will be prohibited in the work zone. Residents with driveways within
the active work zones are asked to relocate their car(s) to an available location on
Roosevelt Street or to a side street by 7 AM.

If you have any questions, please call Todd Wells with Engineering Enterprises, Inc. at
773-454-4214 or City Department of Public Works at 630-377-4405.