Anticipated work for the week of August 29 - September 2:

On Saturday 8/27/2022, the southbound lane of Kautz Road will be removed with road grinders.  The contractor will leave the roadway intact at all driveway entrances. In the future, the City will coordinate the removal and replacement of these driveways and road sections. There will be heavy truck traffic during this operation, but the northbound lane will remain open.

Road Subgrade work will take place, beginning at the railroad tracks and moving north.

Sanitary work will continue near Illinois Ave.  

To date, approximately 90% of the water main is installed and 70% of the sanitary sewer has been completed.

 