Ward 2
Week of October 12, 2015
West Side of Fox River
Avalon Court
Completed – Punchlist items outstanding
8th Street and 8th Court
Completed – Punchlist items outstanding
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Completed
East Side of Fox River
Walnut Ave.
Completed – Punchlist items outstanding
Crabapple Ln.
Completed – Punchlist items outstanding
S. 10th Ave
Completed – Punchlist items outstanding
Stone Dr. and DuKane Dr.
Week of September 28, 2015
West Side of Fox River
Avalon Court
Minor sidewalk repair.
8th Street and 8th Court
Completed – Punchlist items outstanding.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Completed
East Side of Fox River
Walnut Ave.
Completed – Punchlist items outstanding.
Crabapple Ln.
Minor sidewalk and curb repair.
S. 10th Ave
Completed – Punchlist items outstanding.
Stone Dr. and DuKane Dr.
Week of September 7, 2015
EAST SIDE OF FOX RIVER
Tyler Road
The work completed for the week ending September 5, 2015 included the installation of watermain from Allen Lane south to Wing Lane. Flushing and pressure testing of the watermain began on the north end of the project.
The scheduled work for the week ending September 12, 2015 will include the continued installation of watermain to the south.
Week of August 31, 2015
West Side of Fox River
Avalon Court
No work this week. Restoration 1st and 2nd week of September.
8th Street and 8th Court
No work this week. Restoration 1st and 2nd week of September.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
No work this week. Restoration 1st and 2nd week of September.
Week of August 24, 2015
West Side of Fox River
Avalon Court
No work this week
8th Street and 8th Court
No work this week
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
No work this week
East Side of Fox River
Walnut Ave.
Hot Mix Asphalt roadway surface pavement paving.
Crabapple Ln.
No work this week.
S. 10th Ave
Hot Mix Asphalt roadway surface pavement paving.
Stone Dr. and DuKane Dr.
Week of August 17, 2015
West Side of Fox River
Avalon Court
No work this week.
8th Street and 8th Court
No work this week.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
No work this week.
East Side of Fox River
Walnut Ave.
Hot Mix Asphalt pavement grinding.
Hot Mix Asphalt pavement paving.
Crabapple Ln.
No work this week.
S. 10th Ave
Hot Mix Asphalt pavement grinding.
Hot Mix Asphalt pavement paving.
Week of August 10, 2015
West Side of Fox River
Avalon Court
No work this week.
8th Street and 8th Court
No work this week.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
No work this week.
East Side of Fox River
Walnut Ave.
Concrete pavement base. HMA pavement grinding. Brick sidewalk repair.
Crabapple Ln.
No work this week.
S. 10th Ave
Concrete sidewalk repair.
Week of August 3, 2015
The work completed for the week ending August 1, 2015 included starting on the Marion Avenue connection as well as the fire hydrant installation at this location. Flushing and pressure testing of the new watermain has begun. The contractor has begun restoration of curb and gutter.
Week of August 3, 2015
West Side of Fox River
Avalon Court
Paving complete, Restoration September 1st.
8th Street and 8th Court
Paving complete, Restoration September 1st.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Paving complete, Restoration September 1st.
East Side of Fox River
Walnut Ave.
No work this week.
Crabapple Ln.
Paving complete, Restoration September 1st.