Week of November 9, 2015

For this weeks update we are breaking the project down into three sections:

Northern Project Limits (S of Country Club Road to Cemetery)

The contractor is currently wrapping up the installation of the new water services in this area, which will be followed up by restoration of the parkways and landscape restoration next week. The work in this general area is wrapping up and the contractor will continue to progress south.

Middle Project Limits (Cemetery to South of Allen Lane)

The installation of the watermain is completed in this section and we are in the process of completing the appropriate testing of the new watermain. The contractor has started replacing the temporary pavement patches with permanent patches. When the permanent patches are installed they are covered with steel plate to protect the patch so it has time to harden. The plates will be in place for a few days and will be removed as early as we possibly can. Next week the contractor will be focusing on the installation of water services in this area.

Southern Project Limits (South of Allen Lane to North Avenue)

The installation of the watermain is completed in this section and this section will be tested next week. Pending all approvals water services will begin later in the week.

created Nov 06, 2015 updated Mar 23, 2018