Next week the contractor will perform the following:
Adams Ave/Ct: No work anticipated.
Dover Hill Ct: No work anticipated.
Fox Chase Dr: Driveway replacements to be completed.
Jackson Ave: Utility repairs to be completed.
Jewel Ave: Utility repairs to be completed. Concrete replacement to be completed.
N. 12th Ave: Concrete removal and replacements to begin.
Mildred Ave: Utility repairs may begin.
Persimmon Dr: No work anticipated.
Rita Ave: Utility repairs may begin.
Ronzheimer Ave: Driveway replacements to be completed.
Ruth Ave: Utility repairs to be completed. Concrete replacement to be completed.
Spring Ave: Utility repairs to be completed.