You are here

Update - 7/13/18

Next week the contractor will perform the following:

Adams Ave/Ct: No work anticipated.
Dover Hill Ct:  No work anticipated.
Fox Chase Dr:  Driveway replacements to be completed.
Jackson Ave:  Utility repairs to be completed.
Jewel Ave:  Utility repairs to be completed.  Concrete replacement to be completed.
N. 12th Ave:  Concrete removal and replacements to begin.
Mildred Ave:  Utility repairs may begin.
Persimmon Dr:  No work anticipated.
Rita Ave:  Utility repairs may begin.
Ronzheimer Ave:  Driveway replacements to be completed.
Ruth Ave:  Utility repairs to be completed.  Concrete replacement to be completed.
Spring Ave: Utility repairs to be completed.

created Jul 16, 2018 updated Jul 16, 2018