Next week the contractor will perform the following:

Adams Ave/Ct: Concrete removal and replacements to continue.  Utility repairs to continue.  Asphalt removal and replacement may begin.
Dover Hill Ct:  Concrete removal and replacements to begin.  Utility repairs to begin.  Asphalt removal and replacement may begin.
Fox Chase Dr:  Asphalt removal and replacement to continue.
Jackson Ave:  Concrete removal and replacements to begin.  Asphalt removal and replacement may begin.
Jewel Ave:  Asphalt removal and replacement to begin.
N. 12th Ave:  Asphalt removal and replacement to begin.
Mildred Ave:  Asphalt removal and replacement to continue.
Persimmon Dr:  Concrete removal and replacements to begin. 
Rita Ave:  Asphalt removal and replacement to continue.
Ronzheimer Ave:  Asphalt removal and replacement to continue.
Ruth Ave:  Asphalt removal and replacement to begin.
Spring Ave: Concrete removal and replacements to begin. Asphalt removal and replacement may begin.

 