Next week the contractor will perform the following:

Adams Ave/Ct:.  Asphalt removal and replacement to begin.
Dover Hill Ct:  Asphalt removal and replacement to begin.
Fox Chase Dr:  Asphalt replacement to be completed.
Jackson Ave:   Asphalt removal and replacement to be completed.
Jewel Ave:  Asphalt removal and replacement to be completed.
N. 12th Ave:  Asphalt removal and replacement to be completed.
Mildred Ave:  No work anticipated.
Persimmon Dr:  Asphalt removal and replacement to be completed. 
Rita Ave:  No work anticipated.
Ronzheimer Ave:  No work anticipated.
Ruth Ave:  Asphalt removal and replacement to be completed.
Spring Ave: Asphalt removal and replacement to begin.
All Streets:  Sod restoration to be completed in early September.