Update - 7/16/20

Anticipated construction work for the week of July 20 – July 24

Please Note: All work contingent on weather

East Side Streets

  • N. 2nd Ave. – No work at this time
  • Edward Ave. – Landscape restoration
  • Fox Glen Dr. – Landscape restoration, asphalt surface
  • King Richard Circle – Landscape restoration
  • Queen Elizabeth Ct. - Landscape restoration
  • Pinelands Rd. - No work at this time

West Side Streets

  • Fairview Dr. – Utility repair work
  • Heritage St./Ct. - Landscape restoration, asphalt surface
  • Horne St. – Utility repair work
  • Killdeer Ln. – Landscape restoration, asphalt surface
  • S. 12th St. – No work at this time
  • S. 19th Street – Utility repair work
  • Tradition Blvd. – Landscape restoration
created Jul 16, 2020 updated Jul 16, 2020